Multiple Choice
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by as hammock activity. Which is a legitimate hammock activity for this project?
A) combine activities A, B, C
B) combine activities B, E, H
C) combine activities E, F
D) combine activities G, H, I
Correct Answer:

Verified
Correct Answer:
Verified