Multiple Choice
Activities C, D, and E in the project represented by the network are to be hammocked. What are the late start and early finish times of the hammock activity?
A) 6, 24
B) 6, 26
C) 8, 24
D) 8, 26
Correct Answer:

Verified
Correct Answer:
Verified