A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?
A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36