Multiple Choice
Which of the following statements regarding project life cycles is most accurate?
A) All research and development organizations rely upon a four-stage project life cycle that includes initiating, planning, executing and closing.
B) The project life cycle is the same regardless of the type of projects managed by an organization.
C) The control needs of an organization determine the name and number of phases in the project life cycle that it adopts.
D) All project life cycles are the same across every industry
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Achieving project success is determined by all
Q10: Projects consist of the ongoing work needed
Q11: Human Resource management is comprised of the
Q12: The project manager is typically the person
Q13: Integration management represents the processes and activities
Q18: Typically,the person or group that provides the
Q20: Projects often require tradeoffs among all of
Q21: A project is a lasting endeavor undertaken
Q21: Different project life cycle models are used
Q45: Projects are considered successful for all of