Which of the Following Items Best Depicts the Define Scope

Question 44

Multiple Choice

Which of the following items best depicts the Define Scope process?


A) It begins by determining product scope / deliverables and culminates in a project scope statement.
B) It begins by establishing a scope baseline and culminates in scope verification.
C) It begins with user requirements and culminates in a product specification.
D) It begins with a business case and culminates in a project charter