Which of the Following Items Best Describes a Project Work

Question 42

Multiple Choice

Which of the following items best describes a project Work Breakdown Structure (WBS) ?


A) an organizational chart depicting who will perform project work
B) a schedule depicting when project work will be performed
C) a framework that identifies project deliverables
D) a list of activities to complete the project work packages

Correct Answer: