Multiple Choice
Work Breakdown Structures can be displayed in a variety of formats including which of the following?
A) an indented outline format
B) an inverted pyramid
C) a sequential process diagram
D) fishbone or cause and effect diagram
Correct Answer:

Verified
Correct Answer:
Verified