Multiple Choice
Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?
A) Define activities
B) Sequence activities
C) Estimate activity duration
D) Create WBS
Correct Answer:

Verified
Correct Answer:
Verified