Multiple Choice
When estimating resource needs,project teams should consider all the following EXCEPT:
A) supporting needs like information systems.
B) the time required to communicate between activities.
C) specific knowledge or skills that must be secured.
D) scoring models
Correct Answer:

Verified
Correct Answer:
Verified