________ Is an Analytical Method That Determines the Probabilities of the Project

Question 1

Multiple Choice

________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time is normal using the central limit theorem.


A) Program Estimation and Research Technique
B) Project Evaluation and Revise Technique
C) Program Evaluation and Review Technique
D) Project Estimation and Risk Technique

Correct Answer:

verifed

Verified