The Budget at Completion (BAC) is the sum of all budgeted values established for the work to be performed on a project.As such it is equivalent to:
A) the total planned value of the project.
B) the total earned value of the project.
C) the total actual cost of the project.
D) the total value of the work completed to date
Correct Answer:

Verified
Correct Answer:
Verified