    What Is the Slack Time for Activity B Given the Activity
Solved

What Is the Slack Time for Activity B Given the Activity

Question 98

Question 98

Multiple Choice

What is the slack time for Activity B given the activity times and precedence requirements shown in the table? What is the slack time for Activity B given the activity times and precedence requirements shown in the table?   A) 7 B) 6 C) 5 D) 4


A) 7
B) 6
C) 5
D) 4

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q10: The PERT technique assumes that durations are

Q94: Concurrent activities are:<br>A)activities that must be done

Q95: Thanks to excessive dilly dallying,the subcontractor grossly

Q96: Use the values in the table to

Q97: The best candidate activities for shortening the

Q99: One approach to reducing project length would

Q100: In order to reduce the length of

Q101: Project Test Bank is composed of activities

Q102: A gentleman farmer maniacally works on academic

Q103: An activity has an optimistic time estimate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines