    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    One Approach to Reducing Project Length Would Be To
Solved

One Approach to Reducing Project Length Would Be To

Question 99

Question 99

Multiple Choice

One approach to reducing project length would be to:


A) convert parallel paths to be serial.
B) convert merge activities to burst activities.
C) use hammock activities in place of multiple activities.
D) eliminate tasks on the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33: At a burst point in a backward

Q94: Concurrent activities are:<br>A)activities that must be done

Q95: Thanks to excessive dilly dallying,the subcontractor grossly

Q96: Use the values in the table to

Q97: The best candidate activities for shortening the

Q98: What is the slack time for Activity

Q100: In order to reduce the length of

Q101: Project Test Bank is composed of activities

Q102: A gentleman farmer maniacally works on academic

Q103: An activity has an optimistic time estimate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines