menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    Use the Network Diagram and Activity Lengths in the Nodes
Solved

Use the Network Diagram and Activity Lengths in the Nodes

Question 49

Question 49

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.   A) 12 B) 13 C) 14 D) 15


A) 12
B) 13
C) 14
D) 15

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: At a merge point in a forward

Q44: In general,the better candidates for shortening are:<br>A)early

Q45: _ activities have two or more immediate

Q46: In the beta distribution,the longer tail is

Q48: Because an activity's pessimistic estimate may represent

Q50: Use the network diagram and activity lengths

Q51: What is the late finish time for

Q52: There is no slack on the project

Q53: Use the network diagram and activity lengths

Q54: Activities C,D,and E in the project represented

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines