    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    What Is the Late Finish Time for Activity D Given
Solved

What Is the Late Finish Time for Activity D Given

Question 51

Question 51

Multiple Choice

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?   A) 14 B) 13 C) 12 D) 11


A) 14
B) 13
C) 12
D) 11

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: At a merge point in a forward

Q46: In the beta distribution,the longer tail is

Q48: Because an activity's pessimistic estimate may represent

Q49: Use the network diagram and activity lengths

Q50: Use the network diagram and activity lengths

Q52: There is no slack on the project

Q53: Use the network diagram and activity lengths

Q54: Activities C,D,and E in the project represented

Q55: What is the slack time for Activity

Q56: A project has the precedence requirements and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines