Multiple Choice
It took 66 hours of analysis to complete the first phase,but the second phase was done in 56.1 hours.If this learning rate continues,then the 8th analysis should take a mere:
A) 40 hours and 30 minutes,give or take.
B) 44 hours and 20 minutes,give or take.
C) 40 hours and 15 minutes,give or take.
D) 38 hours and 45 minutes,give or take.
Correct Answer:

Verified
Correct Answer: