Multiple Choice
Project cost estimates usually anticipate that resources will be available,that the weather will not be extreme,and that funding will materialize,creating what are called:
A) hyperactivity.
B) standard operating procedures.
C) standard duress.
D) normal conditions.
Correct Answer:

Verified
Correct Answer:
Verified