Multiple Choice
It was fortunate that the project budget included contingency funding;the top manager had not foreseen that the project would need the services of their elite slide rule squad in more than one area at the same time.Design couldn't complete their work without their services,nor could marketing,or production.Contingency funds came in handy to meet the unanticipated:
A) change in project scope.
B) abnormal project conditions.
C) consequences of Murphy's Law.
D) interaction costs.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: A contingency rate of 10% on a
Q22: What are three benefits to the use
Q53: What's the relationship between WBS,scheduling,and budgeting?
Q55: What are four major categories of costs?
Q102: What is the total amount budgeted for
Q103: Project cost estimates usually anticipate that resources
Q106: It took 66 hours of analysis to
Q107: A plan that identifies the allocated resources,the
Q109: An advantage of top-down budgeting is:<br>A)that top
Q110: Overhead and selling and administration are classified