Multiple Choice
An early warning signal for the potential of an overdrawn budget is created when:
A) activity-based costing cannot identify drivers.
B) a bottom-up budget never makes it up the chain of command.
C) contingency funds are applied for.
D) a top-down process moves too quickly down to the functional managers.
Correct Answer:

Verified
Correct Answer:
Verified