    The Expected Cost of an Item That Is Estimated at $5,000
Solved

The Expected Cost of an Item That Is Estimated at $5,000

Question 14

Question 14

Multiple Choice

The expected cost of an item that is estimated at $5,000 with a task contingency multiplier of 1.2 is:


A) $4,167.
B) $5,000.
C) $5,200.
D) $6,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: Risk cannot be transferred because ultimately your

Q10: The programming division at ABC decides to

Q11: The PRAM model for risk management proposes

Q12: A project team assesses their primary risk

Q13: What are fixed-price contracts and liquidated damages?

Q15: Contingency reserves require a construction company to

Q16: The project team toiled long into

Q17: Twenty-thousand dollars was budgeted for the office

Q18: The pointy-haired dean gently suggested that study

Q19: The consequences of failure categories of cost,schedule,reliability,and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines