Multiple Choice
Take the factors considered by earned value analysis and subtract those considered by project S-curves.The factor(s) you have remaining are:
A) performance and cost.
B) cost and schedule.
C) time.
D) performance.
Correct Answer:

Verified
Correct Answer:
Verified