Multiple Choice
Earned value management at the portfolio level requires:
A) a single project manager with a single metric system.
B) aggregation of all earned value measures across the firm's entire project portfolio.
C) only positive variances for both budget and schedule.
D) only negative variances for both budget and schedule.
Correct Answer:

Verified
Correct Answer:
Verified