Multiple Choice
Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project.
A) $7,800
B) $9,600
C) $8,400
D) $6,900
Correct Answer:

Verified
Correct Answer:
Verified