Multiple Choice
Which statement about critical chain methodology is best?
A) Activity durations estimated at a 50% level of successful completion are shorter than those estimated at a 90% level of successful completion.
B) Aggregated activity durations at a 90% level of successful completion are shorter than aggregated activity durations at a 50% level of successful completion.
C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likely level estimate.
D) None of these statements is correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q70: Create a 5-activity example and use it
Q73: The Central Limit Theorem states that if
Q88: What is the difference between common cause
Q89: Use the project information in the table
Q90: A worker is assigned three tasks,A,B,and C,each
Q92: In order to estimate completion of a
Q93: All five members of a project team
Q94: Critical Chain Project Management is based on
Q95: All five members of a project team
Q96: A project is represented by the activity