Multiple Choice
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the overall duration of this project if it is managed using critical chain methodology?
A) 22.5
B) 24.75
C) 27.0
D) 33.75
Correct Answer:

Verified
Correct Answer:
Verified