A Project Is Represented by the Activity Durations (In Days,estimated

Question 20

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?   A) 4 days B) 3 days C) 2 days D) 1 days


A) 4 days
B) 3 days
C) 2 days
D) 1 days

Correct Answer: