Multiple Choice
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?
A) 4 days
B) 3 days
C) 2 days
D) 1 days
Correct Answer:

Verified
Correct Answer:
Verified
Q16: If a project activity experiences negative variation:<br>A)the
Q18: CCPM advocates performing all non-critical activities:<br>A)as late
Q19: A project consists of six consecutive tasks
Q21: Keith welds a one-fourth-inch diameter ball bearing
Q22: A project is represented by the activity
Q23: The Central Limit Theorem says that if
Q24: If a project activity experiences positive variation:<br>A)the
Q25: Under the student syndrome model,the slope of
Q51: Your next project consists of 10 consecutive
Q79: Define and describe the function and interrelationship