Multiple Choice
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.
A) 5 days
B) 6 days
C) 7 days
D) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q16: If a project activity experiences negative variation:<br>A)the
Q18: CCPM advocates performing all non-critical activities:<br>A)as late
Q20: A project is represented by the activity
Q21: Keith welds a one-fourth-inch diameter ball bearing
Q22: A project is represented by the activity
Q23: The Central Limit Theorem says that if
Q24: If a project activity experiences positive variation:<br>A)the
Q31: The legal department is needed to review
Q51: Your next project consists of 10 consecutive
Q79: Define and describe the function and interrelationship