menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 11: Critical Chain Project Scheduling
  5. Question
    A Project Is Represented by the Activity Durations (In Days,estimated
Solved

A Project Is Represented by the Activity Durations (In Days,estimated

Question 2

Question 2

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?   A) 3.5 days B) 2.5 days C) 1.5 days D) 0.5 days


A) 3.5 days
B) 2.5 days
C) 1.5 days
D) 0.5 days

Correct Answer:

verifed

Verified

Related Questions

Q1: All five members of a project team

Q3: A(n)_ refers to a safety margin that

Q4: The _ syndrome describes the tendency to

Q5: A worker is assigned three tasks,A,B,and C,each

Q6: A project is represented by the activity

Q7: Which of the following statement is best?<br>A)The

Q8: Drum buffers are:<br>A)a safety margin separating different

Q9: Which of these is Parkinson's Law?<br>A)Don't put

Q10: An important departure from traditional project management

Q11: A project is represented by the activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines