Multiple Choice
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?
A) a < d
B) a < c
C) b < c
D) d < a
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q11: Quite often the marginal gains in employee
Q15: AOA networks have an advantage over AON
Q17: Use the information in the table to
Q18: Dummy activities have a duration equal to
Q21: A project has the activity duration and
Q22: What is the duration of the project
Q24: What is the minimum completion cost of
Q25: What information is NOT included in the
Q30: What are the three principal methods for
Q37: The critical path may not contain a