    Activity X Has the Start to Finish Relationship Shown with Activity
Solved

Activity X Has the Start to Finish Relationship Shown with Activity

Question 20

Question 20

Multiple Choice

Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best? Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?   A) a < d B) a < c C) b < c D) d < a


A) a < d
B) a < c
C) b < c
D) d < a

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q11: Quite often the marginal gains in employee

Q15: AOA networks have an advantage over AON

Q17: Use the information in the table to

Q18: Dummy activities have a duration equal to

Q21: A project has the activity duration and

Q22: What is the duration of the project

Q24: What is the minimum completion cost of

Q25: What information is NOT included in the

Q30: What are the three principal methods for

Q37: The critical path may not contain a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines