Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?
A) $18,100
B) $19,350
C) $17,416.67
D) $16,110
Correct Answer:

Verified
Correct Answer:
Verified