Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 21

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?   A) $18,100 B) $19,350 C) $17,416.67 D) $16,110


A) $18,100
B) $19,350
C) $17,416.67
D) $16,110

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions