    Dummy Activities Have a Duration Equal to The
Solved

Dummy Activities Have a Duration Equal to The

Question 18

Question 18

Multiple Choice

Dummy activities have a duration equal to the:


A) slack on the critical path.
B) length of the predecessor.
C) length of the successor.
D) lag needed to preserve network logic.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q11: Quite often the marginal gains in employee

Q13: A project has the activity duration and

Q14: What is the late finish for activity

Q15: AOA networks have an advantage over AON

Q17: Use the information in the table to

Q20: Activity X has the start to finish

Q21: A project has the activity duration and

Q22: What is the duration of the project

Q30: What are the three principal methods for

Q37: The critical path may not contain a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines