    What Is the Late Finish for Activity D in the Network
Solved

What Is the Late Finish for Activity D in the Network

Question 14

Question 14

Multiple Choice

What is the late finish for activity D in the network shown in the diagram? What is the late finish for activity D in the network shown in the diagram?   A) 15 B) 16 C) 17 D) 18


A) 15
B) 16
C) 17
D) 18

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: The least common type of lag relationship

Q9: Crashing costs for a project are governed

Q11: A project manager ascertained that five different

Q11: Quite often the marginal gains in employee

Q12: What is the cost to finish this

Q13: A project has the activity duration and

Q15: AOA networks have an advantage over AON

Q17: Use the information in the table to

Q18: Dummy activities have a duration equal to

Q37: The critical path may not contain a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines