Multiple Choice
Eight jobs have been sequenced at a single work centre. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and average jobs in the system is ________.
A) 100% ; 10.625
B) low; .0941
C) 0.400 or 40%; 2.5
D) 0.235 or 23.5%; 4.25
E) maximized; minimized
Correct Answer:

Verified
Correct Answer:
Verified