Which of the following is not a basic element in a project plan?


A) objectives
B) personnel
C) contract requirements
D) All the above are basic elements.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Global projects rarely are concerned with cultural

Q36: Crashing activates with positive slack reduces a

Q40: The following table of probabilistic time estimates

Q43: A project consists of the following four

Q45: A(n)_ is a project team structure that

Q46: A project consists of the following four

Q49: In project management, the slack in an

Q50: The following table of probabilistic time estimates

Q54: The three major components of project management

Q71: What is a scope statement?

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines