Question 40

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, the earliest start (ES)  time for activity D is A)  8.17 weeks. B)  12.67 weeks. C)  18.33 weeks. D)  21.67 weeks.
-Using Table 9.3, the earliest start (ES) time for activity D is


A) 8.17 weeks.
B) 12.67 weeks.
C) 18.33 weeks.
D) 21.67 weeks.

Correct Answer: