Multiple Choice
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the critical path for this project is
A) A-B-C.
B) A-C-D.
C) A-B-D.
D) A-B-C-D.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q8: Briefly describe the makeup of the project
Q12: A Gantt chart provides a visual display
Q36: Crashing activates with positive slack reduces a
Q64: A _ breaks down a project into
Q65: Issues of cultural diversity in project management
Q66: A project consists of the following four
Q68: The following table of probabilistic time estimates
Q72: A project team is typically cross-functional consisting
Q73: A project consists of the following four
Q74: The following table of probabilistic time estimates