Multiple Choice
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the time to complete the entire project would be
A) 23 days.
B) 19 days.
C) 17 days.
D) 11 days.
Correct Answer:

Verified
Correct Answer:
Verified
Q13: For activities on a project's critical path,<br>A)earliest
Q18: A project consists of the following activities:<br>
Q20: A project consists of the following four
Q22: Which of the following is the universal
Q25: The project management process encompasses<br>A)planning.<br>B)scheduling.<br>C)control.<br>D)All of the
Q57: The longest path through a project network
Q64: One disadvantage of Gantt charts,especially for large
Q85: Project scheduling is recognized as the most
Q96: Management and control of a companywide portfolio
Q97: Unlike PERT,CPM incorporates probabilistic time estimates into