Multiple Choice
A project consists of the following four activities with activity times in days:
Table 9.3
-Using Table 9.3,the earliest finish (EF) time for activity C is
A) 4 days.
B) 6 days.
C) 10 days.
D) 11 days.
Correct Answer:

Verified
Correct Answer:
Verified