Multiple Choice
A project consists of the following activities:
Table 9.1
-Using Table 9.1,the latest start (LS) time for activity B is
A) 5 weeks.
B) 8 weeks.
C) 13 weeks.
D) 14 weeks.
Correct Answer:

Verified
Correct Answer:
Verified