Given the Tasks,estimated Durations,and Crash Costs Shown Below,if the Benefit

Question 14

Multiple Choice

Given the tasks,estimated durations,and crash costs shown below,if the benefit to crash the project by each day is a maximum of $750,how many days would it be worthwhile to crash the project? Given the tasks,estimated durations,and crash costs shown below,if the benefit to crash the project by each day is a maximum of $750,how many days would it be worthwhile to crash the project?   A) 0 B) 1 C) 2 D) 3 E) 4


A) 0
B) 1
C) 2
D) 3
E) 4

Correct Answer:

verifed

Verified