Given the Project Plan Shown Below,for Each Task Assume That

Question 18

Multiple Choice

Given the project plan shown below,for each task assume that the best-case duration is 80 percent of the most likely duration,and the worst-case duration is 150 percent of the most likely duration.What is the expected completion time for the critical path? Given the project plan shown below,for each task assume that the best-case duration is 80 percent of the most likely duration,and the worst-case duration is 150 percent of the most likely duration.What is the expected completion time for the critical path?   A) 34 days B) 21.0 days C) 35.7 days D) 22.1 days


A) 34 days
B) 21.0 days
C) 35.7 days
D) 22.1 days