Multiple Choice
Given the project plan shown below,for each task assume that the best-case duration is 80 percent of the most likely duration,and the worst-case duration is 150 percent of the most likely duration.What is the expected completion time for the critical path?
A) 34 days
B) 21.0 days
C) 35.7 days
D) 22.1 days
Correct Answer:

Verified
Correct Answer: