Task X has a most likely duration of 10 days,a best-case duration of 8 days,and a worst-case duration of 15 days.What is the probability that it will be completed in 10 days or less?
A) 0 percent
B) 50.0 percent
C) 33.4 percent
D) 83.4 percent