A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below. The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned?
A) Approximately 85 percent
B) Approximately 5 percent
C) Approximately 2.3 percent
D) Approximately 97.7 percent