Question 22

Multiple Choice

A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below. A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below.   The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned? A) Approximately 85 percent B) Approximately 5 percent C) Approximately 2.3 percent D) Approximately 97.7 percent The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned?


A) Approximately 85 percent
B) Approximately 5 percent
C) Approximately 2.3 percent
D) Approximately 97.7 percent

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions