Multiple Choice
The four tasks below must be completed in order (a single path of tasks) .Given the task information,what is the probability that the path of tasks will be completed in 20 days or less?
A) 34 percent
B) 56.4 percent
C) 50 percent
D) 76.0 percent
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: A simple sequential project (each task must
Q3: Given the tasks,estimated durations,and crash costs shown
Q4: Given the project data below,what is the
Q5: A project manager has discovered that three
Q6: Given the tasks,estimated durations,and crash costs shown
Q8: If a project path has an expected
Q9: Which of the following statements best describes
Q10: Task X has a most likely duration
Q11: A simple sequential project (each task must
Q12: Annie is planning a large surprise party