Multiple Choice
Which one of the following statements about network diagrams is TRUE?
A) In an activity-on-node diagram, the nodes depict precedence relationships as well as activities.
B) In an activity-on-arc diagram, the arcs depict the activities as well as the precedence relationships.
C) In an activity-on-node diagram, "events" are used to denote the end points of arcs.
D) In an activity-on-arc diagram, there is never a need to use "dummy" activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q24: Scope creep is one of the primary
Q71: _ is the smallest unit of work
Q92: The probability that a project will be
Q97: Table 3.7<br> <span class="ql-formula" data-value="\begin{array}
Q98: Table 3.7<br> <span class="ql-formula" data-value="\begin{array}
Q100: Table 3.3<br> <span class="ql-formula" data-value="\begin{array}
Q105: Assuming a beta distribution is being used,if
Q107: Table 3.3<br> <span class="ql-formula" data-value="\begin{array}
Q109: Figure 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 7.2
Q109: Among all the paths of activities in