Multiple Choice
Table 3.3
-Using Table 3.3,what is the largest amount of slack that any activity in the project has?
A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 or more weeks
Correct Answer:

Verified
Correct Answer:
Verified