Multiple Choice
Which of the following statements concerning the critical path in project network is FALSE?
A) There is always only one critical path in a project network.
B) The critical path is the sequence of activities between a project's start and finish that takes the longest to finish.
C) Activities on the critical path have zero slack.
D) Delaying an activity on the critical path delays the entire project.