Solved

Table 313
You Are Responsible for Managing a Project with the the Following

Question 140

Multiple Choice

Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
 Activity  Expected  Time  Immediate  Predecessor (s) A8 B 10 C 7 A,B  D 5 B  E 12 C  F 7 C,D  G 6 E,F  H 10 F \begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 8 & \cdots - \\\text { B } & 10 & - \\\text { C } & 7 & \text { A,B } \\\text { D } & 5 & \text { B } \\\text { E } & 12 & \text { C } \\\text { F } & 7 & \text { C,D } \\\text { G } & 6 & \text { E,F } \\\text { H } & 10 & \text { F } \\\hline\end{array}
-Using Table 3.13,what is the critical path and the expected completion time for this project?


A) A-C-E-G; 33 weeks
B) B-D-F-G; 33 weeks
C) B-C-E-G; 35 weeks
D) B-C-F-H; 34 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions