Multiple Choice
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,what is the critical path and expected completion time for this project?
A) A-D-E; 17 weeks
B) A-C; 18 weeks
C) B-E; 14 weeks
D) A-D-E; 18 weeks
Correct Answer:

Verified
Correct Answer:
Verified