Multiple Choice
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,which activity has the largest slack,and how large is that slack?
A) Activity C; 5 weeks
B) Activity A; 6 weeks
C) Activity B; 4 weeks
D) Activity E; 3 weeks
Correct Answer: